updated 8/24/26: with completed and upcoming work.
In case you missed it, Sleeper Street debuted its new one way route ten days ago plus during construction hours the street will be open to abutters only.
- On Saturday August 15, 2026, Sleeper Street permanently converted to its one way configuration. Vehicle traffic will flow one-way southbound from Seaport Boulevard towards Congress Street.
- The contractors set up traffic controls and the work zone on the northwest side of Sleeper Street.
- Construction working hours are 7am to 3pm Monday through Friday.
- Sleeper Street is restricted to Abutter Access only during work hours of 7am to 3pm Monday through Friday through the end of construction (November).
- Resident Street Parking will be temporarily restricted during construction and will return after substantial completion later this Fall.
- The existing curb and sidewalk on the western side of Sleeper has been demolished and excavated.
- The western side of the roadway on Sleeper Street was milled.
- The contractors will continue excavation and backfilling of the western side of Sleeper Street in tandem with the facade construction at the Boston Children’s Museum.
- The schedule is subject to change based on weather conditions and other factors. Please observe any posted construction signage.
To learn more about the details of the final design on Sleeper Street and to sign up for the Fort Point Streets Project newsletter, visit the project website.
originally published 08.25.26