UPCOMING WORK
This schedule is subject to change based on weather
conditions and other factors.
Week of May 25 and June 1, 2026
- Continue installation of electrical conduit, new curbs, and new sidewalks on the eastern side of A Street.
- Week of June 8, 2026
- Repave and stripe A Street starting at 7pm.
TRAVEL IMPACTS
Temporary parking restrictions and traffic patterns may be required during working hours from 7 am-3 pm on A Street. Repaving and restriping work will occur after 7 pm. All parking restrictions will be posted with at least 48 hours notice. Please observe any posted construction signage.
COMPLETED WORK
Week of May 11 and Week of May 18, 2026
- Completed milling of the roadway on A Street.
- Completed demolition of the sidewalks and began installation of conduit on the east side of A Street.