Friday, May 22, 2026

A Street Improvements Updates: Upcoming & Completed

UPCOMING WORK

This schedule is subject to change based on weather conditions and other factors.

Week of May 25 and June 1, 2026

  • Continue installation of electrical conduit, new curbs, and new sidewalks on the eastern side of A Street.
  • Week of June 8, 2026
  • Repave and stripe A Street starting at 7pm.

TRAVEL IMPACTS

Temporary parking restrictions and traffic patterns may be required during working hours from 7 am-3 pm on A Street. Repaving and restriping work will occur after 7 pm. All parking restrictions will be posted with at least 48 hours notice. Please observe any posted construction signage.

COMPLETED WORK

Week of May 11 and Week of May 18, 2026

  • Completed milling of the roadway on A Street.
  • Completed demolition of the sidewalks and began installation of conduit on the east side of A Street.