Advisory: Boston Wharf Road Roadway Improvement Project May 27 - July 11

The Boston Wharf Road Improvement Project will commence on May 27 with an anticipated completion date of July 11. The project will include excavating, milling, paving, and striping Boston Wharf Road from Autumn Lane to Congress Street, and part of West Service Road. As part of the project, Boston Wharf Road will be a one-way, South-bound road from Autumn Lane to Congress Street for the duration of the excavation scopes of work.

The project schedule is subject to change based on weather and permitting. 

Please view the project schedule and phasing maps for more information. 

Typical Project Work Hours:
  • During Excavation Scopes of Work: 7:00 AM to 3:00 PM
  • During Milling and Paving Scopes of Work: 7:00 PM to 5:00 AM
Noise Levels: Construction will involve the use of heavy machinery and is expected to have the following potential impacts during the project work hours:
  • Engine and equipment operation
  • Back-up alarms (safety requirement)
  • Material loading/unloading
  • Intermittent vibrations from excavation equipment
Traffic Impacts: Boston Wharf Road will be a one-way, South-bound road from Autumn Lane to Congress Street for the duration of the excavation scopes of work. 

Questions? Contact the Seaport TMA, serving the South Boston Waterfront (Seaport & Fort Point),