Monday, November 16, 2026

SLEEPER STREET & A STREET CONSTRUCTION UPDATES

SLEEPER STREET

UPCOMING WORK

  • Electrical conduit and new street light bases will be installed.
  • Sidewalks will be paved in asphalt to provide a fully accessible surface through the Winter until the final concrete can be poured in the Spring.
  • Temporary speed humps with striping will be installed in the roadway on Sleeper Street.

This schedule is subject to change based on weather conditions and other factors. Please observe any posted construction signage.

TRAVEL IMPACTS

  • The sidewalk on the southeast side of Sleeper Street will be temporarily closed off during this phase of construction. Pedestrians will be rerouted to an accessible walkway on the northwest side of Sleeper Street.
  • Sleeper Street has been converted permanently to its one way configuration. General vehicle traffic now flows one-way southbound from Seaport Boulevard towards Congress Street.
  • Parking will remain temporarily restricted during construction and will return after substantial completion this Fall.

COMPLETED WORK

The curbs on the south east side have been set, widening the sidewalks and adding curb extensions.

WINTER IS COMING...

You’ve heard it plenty: “This schedule is subject to change based on weather conditions.” There’s more to this disclaimer than not wanting to work in the rain. For example, freshly poured concrete must undergo multiple stages of transformation in the right conditions in order to achieve its designed strength and functionality.

First, cement is mixed with water, which kick starts a chemical reaction which forms crystals and binds the mix together. During this phase, the concrete is described as plastic and behaves closer to a liquid.

Once poured, the concrete begins to set, losing plasticity and becoming more solid through the process of hydration. Typically after setting, the concrete can handle some load, but requires 28 days of curing to reach its specified strength.

In colder temperatures, both of these processes are slowed, which can prevent the concrete from building proper strength. There is also the risk of freezing, which may cause severe cracking or crumbling.

To ensure the final product is built to last and that the sidewalks can be used during the winter, our engineers and contractors have made the judgement call to pave the sidewalks on Sleeper Street in asphalt as a temporary condition until we can pour concrete come spring.

A STREET

The temporary flex posts installed on A Street are to be replaced with cast-in-place concrete once construction is complete for the Congress Street improvements at the A Street intersection.

 For more information on Congress Street Improvements Project (Crossroads) which includes Sleeper St and A St., and to sign up for the newsletter, visit Congress Street in Fort Point | Boston.gov.

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.